1) 3 : 4 = 0,75 m 6 men a day
2) 0,75 : 6 = 0,125 m 1 man a day
3) 0,125 × 10 = 1,25 m 10 men a day
4) 7 : 1,25 = 5,6 (days)
5,6 ≈ 6 days
It will take 6 days for 10 men to dig a hole 7 meters/
1) 3 : 4 = 0,75 m 6 men a day
2) 0,75 : 6 = 0,125 m 1 man a day
3) 0,125 × 10 = 1,25 m 10 men a day
4) 7 : 1,25 = 5,6 (days)
5,6 ≈ 6 days
It will take 6 days for 10 men to dig a hole 7 meters/